Report_Id: 229911 Est NO 0003 |
Date:10/28/2022 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 229911 | Estimate Number | 0003 | Estimate Type | PROGRESS | ||
District Office | PIKEVILLE (12300) Hayes, Vincent | ||||||
Contractor | CENTRAL BRIDGE CO LLC | ADDR SN 0 VC Code KY0018903 | |||||
1256 MANCHESTER ST PO BOX 4277 | |||||||
LEXINGTON , KY , 40504 | |||||||
Pay Period | 10/08/2022 TO 10/21/2022 | ||||||
Date Approved | 10/26/2022 | ||||||
Primary Proj Number | BR06718512200 | ||||||
Project No. | EMERGENCY | ||||||
Primary County | LETCHER | ||||||
Name of Road | JOHNS FARM ROAD (CR 1851) OVER MILLSTONE CREEK | ||||||
Description | REPLACE BRIDGE (067N00912N) ON JOHNS FARM ROAD (CR-1851) OVE R MILLSTONE CREEK. | ||||||
Date Let | 08/01/2022 | Formal Acceptance | |||||
Date Awarded | 08/01/2022 | Date Work Began | 09/15/2022 | ||||
Date Contract Executed | 08/01/2022 | Open To Traffic | |||||
Date NTP Issued | 08/01/2022 | Actual Completion Date | |||||
Current Contract Amount | $486,909.00 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $486,909.00 |
Total Earnings | $230,561.86 |
$138,301.86 |
$92,260.00 |
|
Percent Complete | 47.35 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $256,347.14 |
Gross Earnings | $230,561.86 |
$138,301.86 |
$92,260.00 |
|
Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $230,561.86 |
$138,301.86 |
$92,260.00 |
|||
Contract Id | 229911 | Change Order Summary |
County | LETCHER | ||||||
Estimate Nbr | 0003 | Project Number | EMERGENCY | |||||||
Contractor | CENTRAL BRIDGE CO LLC | Period | 10/08/2022 TO 10/21/2022 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 229911 | COMMONWEALTH OF KENTUCKY |
County | LETCHER | ||||||
Contract Type | BRRL BRIDGE REPLACEMENT | TRANSPORTATION CABINET |
Primary Project Number | BR06718512200 | ||||||
Estimate Nbr | 0003 | Period | 10/08/2022 TO 10/21/2022 | |||||||
Contractor | CENTRAL BRIDGE CO LLC | |||||||||
Project | BR06718512200 | Fed/State Project Number | EMERGENCY | Category | ||||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
Project | BR06718512200 | Fed/State Project Number | EMERGENCY | Category | 0001 BRIDGE - 067N00912N | |||||||
0005 | DGA BASE | 00001 | TON | 203.00 | 203.000 | 0.000 | 0.000 | 60.00 | 0.00 | |||
0010 | ROADWAY EXCAVATION | 02200 | CUYD | 101.00 | 101.000 | 0.000 | 0.000 | 81.00 | 0.00 | |||
0015 | GRANULAR EMBANKMENT | 02223 | CUYD | 534.00 | 534.000 | 0.000 | 0.000 | 79.00 | 0.00 | |||
0020 | STRUCTURE GRANULAR BACKFILL | 02231 | CUYD | 160.00 | 160.000 | 0.000 | 0.000 | 100.00 | 0.00 | |||
0025 | TEMPORARY SIGNS | 02562 | SQFT | 64.00 | 64.000 | 80.000 | 80.000 | 22.00 | 1,760.00 | |||
0030 | MAINTAIN & CONTROL TRAFFIC | 02650 | LS | 1.00 | 1.000 | 0.200 | 0.400 | 0.600 | 10,000.00 | 2,000.00 | 6,000.00 | |
0035 | PORTABLE CHANGEABLE MESSAGE SIGN | 02671 | EACH | 2.00 | 2.000 | 0.000 | 0.000 | 2,500.00 | 0.00 | |||
0040 | STAKING | 02726 | LS | 1.00 | 1.000 | 0.200 | 0.400 | 0.600 | 8,500.00 | 1,700.00 | 5,100.00 | |
0045 | ARMORED EDGE FOR CONCRETE | 03299 | LF | 24.00 | 24.000 | 0.000 | 0.000 | 138.00 | 0.00 | |||
0050 | FOUNDATION PREPARATION | 08003 | LS | 1.00 | 1.000 | 0.600 | 0.600 | 26,000.00 | 15,600.00 | |||
0055 | CYCLOPEAN STONE RIP RAP | 08019 | TON | 290.00 | 290.000 | 95.800 | 95.800 | 71.50 | 6,849.70 | |||
0060 | PILES-STEEL HP12X53 | 08046 | LF | 290.00 | 290.000 | 181.080 | 181.080 | 133.00 | 24,083.64 | |||
0065 | PILE POINTS-12 IN | 08094 | EACH | 10.00 | 10.000 | 10.000 | 10.000 | 195.00 | 1,950.00 | |||
0070 | CONCRETE-CLASS A | 08100 | CUYD | 38.00 | 38.000 | 36.460 | 36.460 | 1,400.00 | 51,044.00 | |||
0075 | CONCRETE-CLASS AA | 08104 | CUYD | 35.00 | 35.000 | 0.000 | 0.000 | 2,735.00 | 0.00 | |||
0080 | STEEL REINFORCEMENT-EPOXY COATED | 08151 | LB | 10,500.00 | 10,500.000 | 5,357.260 | 5,357.260 | 2.00 | 10,714.52 | |||
0085 | EROSION CONTROL | 21415ND | LS | 1.00 | 1.000 | 0.200 | 0.300 | 0.500 | 13,000.00 | 2,600.00 | 6,500.00 | |
0090 | BEAM ERECTION | 23953EC | EACH | 4.00 | 4.000 | 4.000 | 0.000 | 4.000 | 17,035.00 | 68,140.00 | 68,140.00 | |
0095 | STEEL DIAPHRAGM | 24991ED | EACH | 3.00 | 3.000 | 3.000 | 0.000 | 3.000 | 940.00 | 2,820.00 | 2,820.00 | |
Project | BR06718512200 | Fed/State Project Number | EMERGENCY | Category | 0002 DEMOBILIZATION | |||||||
0100 | MOBILIZATION | 02568 | LS | 1.00 | 1.000 | 0.500 | 0.500 | 1.000 | 30,000.00 | 15,000.00 | 30,000.00 | |
0105 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 9,002.00 | 0.00 | |||
SUBTOT | $92,260.00 |
$230,561.86 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |